1993. 8 |
Reactor structure installation begins |
¡¡ |


 |
| 1994. 8 |
Multi-Purpose Research Reactor is renamed as HANARO |
¡¡ |
| 1995. 2.
2 |
HANARO fuel is loaded |
¡¡ |
| 1995. 2.
8 |
HANARO reaches the initial criticality |
¡¡ |
| 1995. 4.
7
|
Ceremony for the completion of HANARO construction |
¡¡ |
| 1995.
5-12 |
Performance test of HANARO |
¡¡ |
| 1996. 1-
|
Normal operation of HANARO begins |
¡¡ |
| 1996.
5-7 |
TRIGA Mark-¥± was placed shutdown condition and was
closed |
|
1996. 6 -
1998. 7 |
TRIGA Mark-¥² was placed shutdown condition
and was closed |
¡¡ |